Quantitative AptitudeHardSSC CGL Tier 2 · IBPS PO Mains
A and B can do a job in 20 and 30 days. They start together, but A leaves 5 days before completion. If the total wage is ₹8,000, A's share is:
- A. ₹4,000
- B. ₹3,200
- C. ₹4,800
- D. ₹3,000
Correct answer: A. ₹4,000
Total time x satisfies (x − 5)/20 + x/30 = 1, so x = 15. A worked 10 days = 1/2 of the job, B worked 15 days = 1/2, so each gets ₹4,000. Splitting by days (10 : 15) gives A ₹3,200, ignoring their different speeds.
More Time and Work questions
- A and B can do a job in 6 and 8 days. With C's help they finish it in 3 days. If ₹1,200 is paid for the whole job, C's share is:
- A can finish a task in 10 days and B in 15 days. They work on alternate days, A starting first. The task will be finished in:
- A can do a job in 12 days and B in 18 days. They work on alternate days, B beginning first. The job is finished in:
- A can do a job in 10 days and B in 12 days. They work on alternate days, B starting first. The job is completed in:
- A, B and C can do a job in 10, 12 and 15 days respectively. They work one day each in the order A, B, C, A, B, C, and so on. The job is…
- A job needs 156 man-days of work. On day 1, 2 men work; each day 2 more men join than the day before (2, 4, 6, ...). The number of days to…