1 man does as much work as 2 women, and 1 woman does as much as 2 children. If 4 men, 6 women and 8 children finish a job in 10 days, 3 men and 6 women will finish the same job in:
- A. 15 days
- B. 12 days
- C. 18 days
- D. 20 days
Correct answer: A. 15 days
In child-units: man = 4, woman = 2, child = 1. The first team = 16 + 12 + 8 = 36 units, so work = 360. The second team = 12 + 12 = 24 units/day, giving 15 days.
More Time and Work questions
- 8 men and 12 women can finish a job in 10 days, and 6 men and 8 women can finish it in 14 days. One woman working alone will finish it in:
- Pipe A can fill a tank in 10 hours and pipe B can fill it in 15 hours. Opened together, they will fill it in:
- A tap fills a tank in 6 hours, but because of a leak it takes 8 hours. If the tap is closed, the leak alone would empty the full tank in:
- Two inlet pipes can fill a tank in 12 and 15 hours, and an outlet pipe can empty it in 20 hours. If all three are open, the tank fills in:
- Inlet pipes A and B fill an empty tank in 10 and 12 hours, and outlet pipe C empties a full tank in 15 hours. A and B are opened for 3…
- A can do a job in 6 days and B in 9 days. They finish it together and are paid ₹4,500. A's share is: