Quantitative AptitudeModerateSSC CHSL · SBI PO pattern

A is 25% more efficient than B. If B alone can finish a job in 20 days, A alone can finish it in:

  1. A. 15 days
  2. B. 16 days
  3. C. 25 days
  4. D. 17.5 days

Correct answer: B. 16 days

Efficiency ratio A : B = 5 : 4, so time ratio is 4 : 5 and A takes 16 days. Subtracting 25% of the days (15) wrongly applies the percentage to time.