A is 25% more efficient than B, and B is 20% more efficient than C. If C alone can finish a job in 60 days, A and C working together will finish it in:

  1. A. 30 days
  2. B. 20 days
  3. C. 22.2 days
  4. D. 24 days

Correct answer: D. 24 days

Take C = 1 unit, B = 1.2, A = 1.5. Total work = 60 units; A + C = 2.5 units/day gives 24 days. 22.2 days would include B (2.7 units/day).