Quantitative AptitudeVery hardSSC CGL · RRB NTPC · IBPS Clerk
A is 25% more efficient than B, and B is 20% more efficient than C. If C alone can finish a job in 60 days, A and C working together will finish it in:
- A. 30 days
- B. 20 days
- C. 22.2 days
- D. 24 days
Correct answer: D. 24 days
Take C = 1 unit, B = 1.2, A = 1.5. Total work = 60 units; A + C = 2.5 units/day gives 24 days. 22.2 days would include B (2.7 units/day).
More Time and Work questions
- 6 men can complete a job in 15 days. To complete it in 10 days, the number of men needed is:
- 15 men can finish a job in 24 days. After 8 days, 5 men leave. The job is then finished after a total of:
- 1 man does as much work as 2 women, and 1 woman does as much as 2 children. If 4 men, 6 women and 8 children finish a job in 10 days, 3…
- 8 men and 12 women can finish a job in 10 days, and 6 men and 8 women can finish it in 14 days. One woman working alone will finish it in:
- Pipe A can fill a tank in 10 hours and pipe B can fill it in 15 hours. Opened together, they will fill it in:
- A tap fills a tank in 6 hours, but because of a leak it takes 8 hours. If the tap is closed, the leak alone would empty the full tank in: