A can do a job in 20 days and B in 30 days. A works alone for 5 days and then B joins. In how many days in all is the job completed?
- A. 12 days
- B. 14 days
- C. 15 days
- D. 16 days
Correct answer: B. 14 days
A completes 5/20 = 1/4 first. The remaining 3/4 at a joint rate of 1/12 takes 9 days, so the total is 5 + 9 = 14 days. 9 is only the joint stretch.
More Time and Work questions
- A and B can do a job in 20 and 30 days respectively. They start together but A leaves 4 days before the job is complete. The job takes in…
- A, B and C can do a job in 10, 15 and 30 days. A starts alone; B joins 2 days later, and C joins 2 days after B. The whole job is…
- A and B working together can do a task in 10 days, while A alone can do it in 15 days. They work together for 4 days and then A leaves. B…
- A is three times as efficient as B. If B alone takes 24 days to finish a job, A alone will take:
- A is 25% more efficient than B. If B alone can finish a job in 20 days, A alone can finish it in:
- A is 50% more efficient than B. Together they finish a job in 12 days. A alone will take: