A can do a job in 20 days and B in 30 days. A works alone for 5 days and then B joins. In how many days in all is the job completed?

  1. A. 12 days
  2. B. 14 days
  3. C. 15 days
  4. D. 16 days

Correct answer: B. 14 days

A completes 5/20 = 1/4 first. The remaining 3/4 at a joint rate of 1/12 takes 9 days, so the total is 5 + 9 = 14 days. 9 is only the joint stretch.