A, B and C can do a piece of work alone in 10, 15 and 30 days respectively. Working together they will finish it in:

  1. A. 6 days
  2. B. 5 days
  3. C. 10 days
  4. D. 7.5 days

Correct answer: B. 5 days

Combined rate = 1/10 + 1/15 + 1/30 = 6/30 = 1/5, so 5 days. The simple average of the times, 18.33 days, is meaningless for rates.