A, B and C can do a piece of work alone in 10, 15 and 30 days respectively. Working together they will finish it in:
- A. 6 days
- B. 5 days
- C. 10 days
- D. 7.5 days
Correct answer: B. 5 days
Combined rate = 1/10 + 1/15 + 1/30 = 6/30 = 1/5, so 5 days. The simple average of the times, 18.33 days, is meaningless for rates.
More Time and Work questions
- A and B together can do a work in 18 days, B and C together in 24 days, and A and C together in 36 days. All three working together will…
- A works twice as fast as B. Together they complete a job in 18 days. If A alone works on a second, identical job, the number of days A…
- A can do a job in 20 days and B in 30 days. A works alone for 5 days and then B joins. In how many days in all is the job completed?
- A and B can do a job in 20 and 30 days respectively. They start together but A leaves 4 days before the job is complete. The job takes in…
- A, B and C can do a job in 10, 15 and 30 days. A starts alone; B joins 2 days later, and C joins 2 days after B. The whole job is…
- A and B working together can do a task in 10 days, while A alone can do it in 15 days. They work together for 4 days and then A leaves. B…