A and B together can do a job in 12 days. A alone can do it in 20 days. How long will B alone take?
- A. 8 days
- B. 35 days
- C. 16 days
- D. 30 days
Correct answer: D. 30 days
1/B = 1/12 − 1/20 = 8/240, so B takes 30 days.