Quantitative AptitudeEasySSC CGL · RRB NTPC · IBPS
Meera can complete a job in 40 days and Priya alone can complete it in 10 days. In how many days will they finish it together?
- A. 25 days
- B. 8 days
- C. 10 days
- D. 50 days
Correct answer: B. 8 days
Together = ab/(a + b) = 40 × 10/50 = 8 days.
More Time and Work questions
- 20 workers can build a wall in 15 days. How many days will 12 workers (working at the same rate) take?
- A and B together can do a job in 12 days. A alone can do it in 20 days. How long will B alone take?
- A can do a work in 20 days and B in 30 days. They complete it together and are paid ₹1800. What is A's share?
- Karan can complete a job in 15 days and Rohan alone can complete it in 60 days. In how many days will they finish it together?
- A can do a work in 12 days and B in 6 days. They complete it together and are paid ₹2400. What is A's share?
- A, B and C can do a job alone in 6, 12 and 4 days respectively. In how many days will they finish it working together?