6 men working 8 hours a day can finish a job in 20 days. If they work only 4 hours a day, how many days will they take?
- A. 24 days
- B. 43 days
- C. 10 days
- D. 40 days
Correct answer: D. 40 days
Total work = 6 × 8 × 20 = 960 man-hours. At 4 hours a day, days = 960/(6 × 4) = 40.
More Time and Work questions
- Amit can complete a job in 30 days and Karan alone can complete it in 45 days. In how many days will they finish it together?
- Meera can complete a job in 40 days and Priya alone can complete it in 10 days. In how many days will they finish it together?
- 20 workers can build a wall in 15 days. How many days will 12 workers (working at the same rate) take?
- A and B together can do a job in 12 days. A alone can do it in 20 days. How long will B alone take?
- A can do a work in 20 days and B in 30 days. They complete it together and are paid ₹1800. What is A's share?
- Karan can complete a job in 15 days and Rohan alone can complete it in 60 days. In how many days will they finish it together?