15 workers can build a wall in 6 days. How many days will 5 workers (working at the same rate) take?

  1. A. 20 days
  2. B. 18 days
  3. C. 2 days
  4. D. 11 days

Correct answer: B. 18 days

Total work = 15 × 6 = 90 man-days. With 5 workers: 90/5 = 18 days.