Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS
5 men working 8 hours a day can finish a job in 12 days. If they work only 4 hours a day, how many days will they take?
- A. 16 days
- B. 27 days
- C. 24 days
- D. 6 days
Correct answer: C. 24 days
Total work = 5 × 8 × 12 = 480 man-hours. At 4 hours a day, days = 480/(5 × 4) = 24.
More Time and Work questions
- Meera can complete a job in 30 days and Kavita alone can complete it in 45 days. In how many days will they finish it together?
- Amit can complete a job in 15 days and Sneha alone can complete it in 10 days. In how many days will they finish it together?
- 15 workers can build a wall in 6 days. How many days will 5 workers (working at the same rate) take?
- A and B together can do a job in 15 days. A alone can do it in 40 days. How long will B alone take?
- Gurpreet can complete a job in 45 days and Manoj alone can complete it in 90 days. In how many days will they finish it together?
- A pipe can fill a tank in 6 hours and an outlet can empty the full tank in 12 hours. If both are opened together on an empty tank, how…