5 men working 8 hours a day can finish a job in 12 days. If they work only 4 hours a day, how many days will they take?

  1. A. 16 days
  2. B. 27 days
  3. C. 24 days
  4. D. 6 days

Correct answer: C. 24 days

Total work = 5 × 8 × 12 = 480 man-hours. At 4 hours a day, days = 480/(5 × 4) = 24.