A can complete a piece of work in 12 days and B in 20 days. They work together for 3 days, after which A leaves. B alone will finish the remaining work in:
- A. 7.2 days
- B. 12 days
- C. 17 days
- D. 10 days
Correct answer: B. 12 days
Work done together in 3 days = 3 × (1/12 + 1/20) = 0.4. Remaining = 0.6. B's time = 0.6 × 20 = 12 days.
हिंदी में
A किसी कार्य को 12 दिन में और B 20 दिन में पूरा कर सकता है। वे 3 दिन साथ काम करते हैं, उसके बाद A चला जाता है। शेष कार्य B अकेला कितने दिन में पूरा करेगा?
- A. 7.2 days
- B. 12 days
- C. 17 days
- D. 10 days
उत्तर: B. 3 दिन में साथ मिलकर किया कार्य = 3 × (1/12 + 1/20) = 0.4। शेष = 0.6। B का समय = 0.6 × 20 = 12 दिन।
More Time and Work questions
- The efficiencies of A and B are in the ratio 5:3. Together they complete a job in 6 days. How many days will B alone take?
- 40 men can complete a work in 36 days. After 12 days, 60 more men join them. In how many more days will the remaining work be completed?
- A tap fills a tank in 6 hours. Because of a leak at the bottom, it takes 12 hours to fill the tank. The leak alone can empty the full tank…
- 60 men can complete a work in 30 days. After 4 days, 15 more men join them. In how many more days will the remaining work be completed?
- Pipes A and B can fill a tank in 15 hours and 30 hours respectively, while an outlet C can empty the full tank in 30 hours. If all three…
- A can complete a piece of work in 20 days and B in 15 days. They work together for 3 days, after which A leaves. B alone will finish the…