Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
45 men can complete a work in 20 days. After 8 days, 15 more men join them. In how many more days will the remaining work be completed?
- A. 9 days
- B. 12 days
- C. 36 days
- D. 11 days
Correct answer: A. 9 days
Remaining work = 45 men × 12 days = 540 man-days. With 60 men: 540 ÷ 60 = 9 days.
हिंदी में
45 आदमी किसी कार्य को 20 दिन में पूरा कर सकते हैं। 8 दिन बाद 15 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 9 days
- B. 12 days
- C. 36 days
- D. 11 days
उत्तर: A. शेष कार्य = 45 आदमी × 12 दिन = 540 आदमी-दिन। 60 आदमियों के साथ: 540 ÷ 60 = 9 दिन।
More Time and Work questions
- A can complete a piece of work in 24 days and B in 30 days. They work together for 6 days, after which A leaves. B alone will finish the…
- 24 men can complete a work in 45 days. After 10 days, 60 more men join them. In how many more days will the remaining work be completed?
- A and B can complete a work in 15 days and 10 days respectively. They work on alternate days, beginning with A. The work will be completed…
- Pipes A and B can fill a tank in 20 hours and 40 hours respectively, while an outlet C can empty the full tank in 40 hours. If all three…
- A can complete a piece of work in 30 days and B in 60 days. They work together for 3 days, after which A leaves. B alone will finish the…
- A and B can complete a work in 12 days and 6 days respectively. They work on alternate days, beginning with A. The work will be completed…