Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
A can complete a piece of work in 15 days and B in 15 days. They work together for 3 days, after which A leaves. B alone will finish the remaining work in:
- A. 9 days
- B. 10.5 days
- C. 7 days
- D. 12 days
Correct answer: A. 9 days
Work done together in 3 days = 3 × (1/15 + 1/15) = 0.4. Remaining = 0.6. B's time = 0.6 × 15 = 9 days.
हिंदी में
A किसी कार्य को 15 दिन में और B 15 दिन में पूरा कर सकता है। वे 3 दिन साथ काम करते हैं, उसके बाद A चला जाता है। शेष कार्य B अकेला कितने दिन में पूरा करेगा?
- A. 9 days
- B. 10.5 days
- C. 7 days
- D. 12 days
उत्तर: A. 3 दिन में साथ मिलकर किया कार्य = 3 × (1/15 + 1/15) = 0.4। शेष = 0.6। B का समय = 0.6 × 15 = 9 दिन।
More Time and Work questions
- The efficiencies of A and B are in the ratio 2:1. Together they complete a job in 18 days. How many days will B alone take?
- 20 men can complete a work in 30 days. After 6 days, 20 more men join them. In how many more days will the remaining work be completed?
- A, B and C can complete a work alone in 10, 12 and 24 days respectively. They work together and are paid ₹4,500 in all, each in proportion…
- A can complete a piece of work in 24 days and B in 15 days. They work together for 4 days, after which A leaves. B alone will finish the…
- A tap fills a tank in 12 hours. Because of a leak at the bottom, it takes 16 hours to fill the tank. The leak alone can empty the full…
- A can complete a piece of work in 12 days and B in 36 days. They work together for 4 days, after which A leaves. B alone will finish the…