Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
A can complete a piece of work in 12 days and B in 15 days. They work together for 2 days, after which A leaves. B alone will finish the remaining work in:
- A. 10.5 days
- B. 8.5 days
- C. 12 days
- D. 13 days
Correct answer: A. 10.5 days
Work done together in 2 days = 2 × (1/12 + 1/15) = 0.3. Remaining = 0.7. B's time = 0.7 × 15 = 10.5 days.
हिंदी में
A किसी कार्य को 12 दिन में और B 15 दिन में पूरा कर सकता है। वे 2 दिन साथ काम करते हैं, उसके बाद A चला जाता है। शेष कार्य B अकेला कितने दिन में पूरा करेगा?
- A. 10.5 days
- B. 8.5 days
- C. 12 days
- D. 13 days
उत्तर: A. 2 दिन में साथ मिलकर किया कार्य = 2 × (1/12 + 1/15) = 0.3। शेष = 0.7। B का समय = 0.7 × 15 = 10.5 दिन।
More Time and Work questions
- The efficiencies of A and B are in the ratio 2:1. Together they complete a job in 6 days. How many days will B alone take?
- 20 men can complete a work in 24 days. After 6 days, 10 more men join them. In how many more days will the remaining work be completed?
- A and B can complete a work in 30 days and 6 days respectively. They work on alternate days, beginning with A. The work will be completed…
- A and B can complete a work in 10 days and 15 days respectively. They work on alternate days, beginning with A. The work will be completed…
- Pipes A and B can fill a tank in 24 hours and 30 hours respectively, while an outlet C can empty the full tank in 30 hours. If all three…
- A can complete a piece of work in 15 days and B in 15 days. They work together for 4 days, after which A leaves. B alone will finish the…