45 men can complete a work in 30 days. After 8 days, 15 more men join them. In how many more days will the remaining work be completed?
- A. 18.5 days
- B. 66 days
- C. 15 days
- D. 16.5 days
Correct answer: D. 16.5 days
Remaining work = 45 men × 22 days = 990 man-days. With 60 men: 990 ÷ 60 = 16.5 days.
हिंदी में
45 आदमी किसी कार्य को 30 दिन में पूरा कर सकते हैं। 8 दिन बाद 15 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 18.5 days
- B. 66 days
- C. 15 days
- D. 16.5 days
उत्तर: D. शेष कार्य = 45 आदमी × 22 दिन = 990 आदमी-दिन। 60 आदमियों के साथ: 990 ÷ 60 = 16.5 दिन।
More Time and Work questions
- A can complete a piece of work in 24 days and B in 36 days. They work together for 3 days, after which A leaves. B alone will finish the…
- A can complete a piece of work in 20 days and B in 36 days. They work together for 2 days, after which A leaves. B alone will finish the…
- 45 men can complete a work in 36 days. After 12 days, 30 more men join them. In how many more days will the remaining work be completed?
- A can complete a piece of work in 20 days and B in 60 days. They work together for 2 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 3:1. Together they complete a job in 12 days. How many days will B alone take?
- A, B and C can complete a work alone in 10, 24 and 40 days respectively. They work together and are paid ₹4,500 in all, each in proportion…