A does 40% of a job in 8 days, and B finishes the remaining work in 6 days. How long would they take to do the whole job together?
- A. 7 days
- B. 14 days
- C. 6 days
- D. 20/3 days
Correct answer: D. 20/3 days
A alone = 20 days. B does 60% in 6 days, so B alone = 10 days. Together: 20 × 10/30 = 20/3 days (6⅔).
हिंदी में
A किसी कार्य का 40% भाग 8 दिन में करता है, और B शेष कार्य 6 दिन में पूरा करता है। वे दोनों साथ मिलकर पूरा कार्य कितने समय में करेंगे?
- A. 7 दिन
- B. 14 दिन
- C. 6 दिन
- D. 20/3 दिन
उत्तर: D. A अकेला = 20 दिन। B 6 दिन में 60% करता है, इसलिए B अकेला = 10 दिन। साथ में: 20 × 10/30 = 20/3 दिन (6⅔)।
More Time and Work questions
- Working 6 hours a day, a man finishes a job in 10 days. In how many days will he finish it working 7.5 hours a day?
- 12 carpenters working 8 hours a day make 360 chairs in 15 days. How many days will 16 carpenters working 9 hours a day take to make 540…
- A can finish a job in 10 days, and B is 25% more efficient than A. How long will B take alone?
- A tap fills 3/4 of a tank in 12 minutes. How much longer will it take to fill the rest?
- Typist A types 36 pages in 3 hours and typist B types 45 pages in 5 hours. Working together, how long will they take to type 189 pages?
- A tailor stitches 8 shirts a day and his helper 5. For an order of 146 shirts, the tailor works alone for the first 2 days and then the…