A is 40% more efficient than B, and C is 20% less efficient than B. If B alone takes 44 days to finish a job, how long will A and C take together?
- A. 22 days
- B. 24 days
- C. 20 days
- D. 18 days
Correct answer: C. 20 days
Take B's rate as 1 unit: A = 1.4, C = 0.8, so A + C = 2.2 units. Time = 44 ÷ 2.2 = 20 days.
हिंदी में
A, B से 40% अधिक कुशल है, और C, B से 20% कम कुशल है। यदि B अकेला किसी कार्य को 44 दिन में पूरा करता है, तो A और C साथ मिलकर कितना समय लेंगे?
- A. 22 दिन
- B. 24 दिन
- C. 20 दिन
- D. 18 दिन
उत्तर: C. B की दर 1 इकाई मानें: A = 1.4, C = 0.8, इसलिए A + C = 2.2 इकाई। समय = 44 ÷ 2.2 = 20 दिन।
More Time and Work questions
- Pipe A alone fills a tank in 12 hours. When the tank is half full, pipe B, which can fill it alone in 6 hours, is also opened. How long…
- Pipes A and B fill a tank in 20 and 25 minutes. A is opened first. After how many minutes should B be opened so that the tank is full…
- 40 workers can build a road in 60 days. After 15 days, 10 workers leave; after another 15 days, 20 new workers join. In how many days in…
- A can do a job in 18 days. B is 50% more efficient than A, and C is only half as efficient as A. How long will all three take together?
- A can do a job in 10 days and B in 15 days. They work together, but A takes a 2-day break in between. How many days does the job take?
- A job is done if A works 4 days and B works 6 days, or if A works 6 days and B works 3 days. How long would A take alone?