A job is done if A works 4 days and B works 6 days, or if A works 6 days and B works 3 days. How long would A take alone?
- A. 12 days
- B. 8 days
- C. 10 days
- D. 9 days
Correct answer: B. 8 days
4a + 6b = 1 and 6a + 3b = 1. Doubling the second: 12a + 6b = 2. Subtracting the first: 8a = 1, so A takes 8 days (B takes 24).
हिंदी में
कार्य पूरा हो जाता है यदि A 4 दिन और B 6 दिन काम करे, या यदि A 6 दिन और B 3 दिन काम करे। A अकेला कितना समय लेगा?
- A. 12 दिन
- B. 8 दिन
- C. 10 दिन
- D. 9 दिन
उत्तर: B. 4a + 6b = 1 और 6a + 3b = 1। दूसरे समीकरण को दोगुना करने पर: 12a + 6b = 2। पहले को घटाने पर: 8a = 1, इसलिए A को 8 दिन लगेंगे (B को 24)।
More Time and Work questions
- A is 60% more efficient than B, and together they finish a job in 12 days. How long would B take alone?
- A is 25% faster than B, and together they finish a job in 20 days. A works alone for 9 days and B then finishes the job. How many days…
- A can do a job in 20 days and B in 30 days. Owing to a power cut, both work at only 80% of their usual efficiency. How long will they take…
- A can do a job in 18 days and B is 50% more efficient than A. They start together; after some days A leaves and B finishes the rest in 4…
- 16 men working 9 hours a day dig a 72 m trench in 30 days. How many men working 12 hours a day can dig a 96 m trench in 24 days?
- A and B are paid ₹2,400 for a job that A alone can do in 8 days and B alone in 12 days. They work together, but A leaves 2 days before the…