Quantitative AptitudeHardSSC CGL · SSC CHSL
16 men working 9 hours a day dig a 72 m trench in 30 days. How many men working 12 hours a day can dig a 96 m trench in 24 days?
- A. 24
- B. 20
- C. 18
- D. 16
Correct answer: B. 20
Each metre takes 16 × 9 × 30/72 = 60 man-hours. 96 m need 5,760 man-hours; 24 × 12 = 288 hours per man, so 20 men.
हिंदी में
प्रतिदिन 9 घंटे काम करने वाले 16 आदमी 30 दिन में 72 m लंबी खाई खोदते हैं। प्रतिदिन 12 घंटे काम करने वाले कितने आदमी 24 दिन में 96 m लंबी खाई खोद सकते हैं?
- A. 24
- B. 20
- C. 18
- D. 16
उत्तर: B. प्रत्येक मीटर में 16 × 9 × 30/72 = 60 आदमी-घंटे लगते हैं। 96 m के लिए 5,760 आदमी-घंटे चाहिए; प्रति आदमी 24 × 12 = 288 घंटे, इसलिए 20 आदमी।
More Time and Work questions
- A and B are paid ₹2,400 for a job that A alone can do in 8 days and B alone in 12 days. They work together, but A leaves 2 days before the…
- A does one-third of a job in 4 days. Then his efficiency rises by 50%. How many days does he take for the whole job?
- A can do a job in 12 days. With B's help he can do it in 8 days, and with C's help in 6 days. How long will B and C take together, without…
- The efficiencies of A and B are in the ratio 4 : 3, and A finishes a job 6 days sooner than B. How long will they take together?
- A group of men can finish a job in a certain number of days. With 6 more men it would be done 5 days earlier, and with 4 fewer men it…
- Ram does 1/3 of a job in 5 days. Shyam then does 2/5 of the remaining work in 4 days, and Mohan finishes the rest in 6 days. How long…