Quantitative AptitudeHardSSC CGL · SSC CHSL
A can do a job in 12 days. With B's help he can do it in 8 days, and with C's help in 6 days. How long will B and C take together, without A?
- A. 7 days
- B. 9 days
- C. 4.8 days
- D. 8 days
Correct answer: D. 8 days
B = 1/8 − 1/12 = 1/24 and C = 1/6 − 1/12 = 1/12. B + C = 3/24 = 1/8, so 8 days.
हिंदी में
A किसी कार्य को 12 दिन में कर सकता है। B की सहायता से वह उसे 8 दिन में और C की सहायता से 6 दिन में कर सकता है। A के बिना B और C साथ मिलकर कितना समय लेंगे?
- A. 7 दिन
- B. 9 दिन
- C. 4.8 दिन
- D. 8 दिन
उत्तर: D. B = 1/8 − 1/12 = 1/24 और C = 1/6 − 1/12 = 1/12। B + C = 3/24 = 1/8, इसलिए 8 दिन।
More Time and Work questions
- The efficiencies of A and B are in the ratio 4 : 3, and A finishes a job 6 days sooner than B. How long will they take together?
- A group of men can finish a job in a certain number of days. With 6 more men it would be done 5 days earlier, and with 4 fewer men it…
- Ram does 1/3 of a job in 5 days. Shyam then does 2/5 of the remaining work in 4 days, and Mohan finishes the rest in 6 days. How long…
- A and B together can finish a job in 12 days. If A works for 3 days and B for 6 days, 7/20 of the job is done. How long would A take alone?
- A contractor has 30 days to finish a project and employs 50 men working 8 hours a day. After 18 days only 2/5 of the work is done. How…
- A takes 5 days more than B and 9 days more than C to do a job alone. A and B together take as long as C alone. How long does A take alone?