Quantitative AptitudeHardSSC CGL · SSC CHSL
The efficiencies of A and B are in the ratio 4 : 3, and A finishes a job 6 days sooner than B. How long will they take together?
- A. 12 days
- B. 21 days
- C. 72/7 days
- D. 10 days
Correct answer: C. 72/7 days
Times are in the ratio 3 : 4, a difference of 1 part = 6 days. So A = 18 and B = 24 days. Together: 18 × 24/42 = 72/7 days.
हिंदी में
A और B की कार्यक्षमताओं का अनुपात 4 : 3 है, और A किसी कार्य को B से 6 दिन पहले पूरा करता है। साथ मिलकर वे कितना समय लेंगे?
- A. 12 दिन
- B. 21 दिन
- C. 72/7 दिन
- D. 10 दिन
उत्तर: C. समयों का अनुपात 3 : 4 है, अंतर 1 भाग = 6 दिन। इसलिए A = 18 और B = 24 दिन। साथ में: 18 × 24/42 = 72/7 दिन।
More Time and Work questions
- A group of men can finish a job in a certain number of days. With 6 more men it would be done 5 days earlier, and with 4 fewer men it…
- Ram does 1/3 of a job in 5 days. Shyam then does 2/5 of the remaining work in 4 days, and Mohan finishes the rest in 6 days. How long…
- A and B together can finish a job in 12 days. If A works for 3 days and B for 6 days, 7/20 of the job is done. How long would A take alone?
- A contractor has 30 days to finish a project and employs 50 men working 8 hours a day. After 18 days only 2/5 of the work is done. How…
- A takes 5 days more than B and 9 days more than C to do a job alone. A and B together take as long as C alone. How long does A take alone?
- A is twice as efficient as B, and B is twice as efficient as C. A finishes a job 30 days sooner than C. How long will all three take…