Cost and Management AccountingHard
Annual demand is 4,500 units, ordering or set-up cost per batch is Rs 100 and carrying cost per unit per year is Rs 10. The economic batch quantity is:
- A. 200 units
- B. 300 units
- C. 450 units
- D. 600 units
Correct answer: B. 300 units
EBQ = square root of (2 x 4,500 x 100 / 10) = square root of 90,000 = 300 units.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- Abnormal loss in a process is:
- Using the weighted average method, total cost of opening WIP and current period is Rs 60,000 and equivalent units are 1,000. The value of…
- Estimated total profit on a contract is Rs 2,00,000. Work certified is Rs 12,00,000 and contract price is Rs 15,00,000. Profit to be…
- 1,000 units are introduced, normal loss is 10%, 800 units are completed and 80 units remain in WIP at 50% conversion (materials fully…
- A job uses 25 machine hours at Rs 80 per hour, direct materials Rs 12,000 and direct labour Rs 6,000. If profit is 20% on selling price…
- In a cost-plus contract, the contractee pays the contractor: