A contract of price Rs 12,00,000 has estimated total cost Rs 14,00,000 with cost incurred to date of Rs 9,00,000. Loss to be recognised is:
- A. Rs 67,000 pro rata
- B. Nil until completion
- C. The full expected loss of Rs 2,00,000 immediately
- D. Rs 1,00,000
Correct answer: C. The full expected loss of Rs 2,00,000 immediately
Prudence requires that expected loss on a contract be recognised in full as soon as it is foreseen.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- The scrap value of normal loss in a process is:
- A lorry runs 30 days a month, each day carrying 10 tonnes over 100 km outward and returning empty. Monthly cost is Rs 90,000. Cost per…
- Process A transfers 1,000 units to Process B at Rs 40 per unit, which includes Rs 10 profit over cost. 400 of those units remain in…
- On a contract, materials consumed are Rs 2,00,000, wages paid Rs 1,50,000 with Rs 10,000 accrued, plant depreciation Rs 20,000 and…
- Opening WIP is 100 units (materials 100%, conversion 40%), 900 units are started, 800 are completed and closing WIP is 200 units…
- A taxi has fixed charges of Rs 8,000 per month and variable cost of Rs 3 per km. If it runs 4,000 km in a month, total cost per km is: