Cost and Management AccountingHard
On a contract, materials consumed are Rs 2,00,000, wages paid Rs 1,50,000 with Rs 10,000 accrued, plant depreciation Rs 20,000 and overhead is 10% of wages (including accrued). Total cost to date is:
- A. Rs 3,86,000
- B. Rs 3,70,000
- C. Rs 3,96,000
- D. Rs 4,06,000
Correct answer: C. Rs 3,96,000
Wages = 1,60,000. Overhead = 16,000. Total = 2,00,000 + 1,60,000 + 20,000 + 16,000 = Rs 3,96,000.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- Opening WIP is 100 units (materials 100%, conversion 40%), 900 units are started, 800 are completed and closing WIP is 200 units…
- A taxi has fixed charges of Rs 8,000 per month and variable cost of Rs 3 per km. If it runs 4,000 km in a month, total cost per km is:
- Materials returned from the contract site to the stores are:
- Input is 2,000 units, normal loss 10% at the start (no scrap), completed units 1,500, closing WIP 200 units 60% converted (materials 100%)…
- In contract costing, work certified means:
- A school bus incurs Rs 72,000 a month, carries an average of 30 students and covers 2,400 km a month. Cost per student-km is: