Cost and Management AccountingHard

On a contract, materials consumed are Rs 2,00,000, wages paid Rs 1,50,000 with Rs 10,000 accrued, plant depreciation Rs 20,000 and overhead is 10% of wages (including accrued). Total cost to date is:

  1. A. Rs 3,86,000
  2. B. Rs 3,70,000
  3. C. Rs 3,96,000
  4. D. Rs 4,06,000

Correct answer: C. Rs 3,96,000

Wages = 1,60,000. Overhead = 16,000. Total = 2,00,000 + 1,60,000 + 20,000 + 16,000 = Rs 3,96,000.