Cost and Management AccountingVery hard
Opening WIP is 100 units (materials 100%, conversion 40%), 900 units are started, 800 are completed and closing WIP is 200 units (materials 100%, conversion 50%). Equivalent units for conversion under FIFO are:
- A. 860
- B. 800
- C. 900
- D. 960
Correct answer: A. 860
Opening WIP needs 100 x 60% = 60. Started and completed = 700. Closing WIP = 200 x 50% = 100. Total = 860.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- A taxi has fixed charges of Rs 8,000 per month and variable cost of Rs 3 per km. If it runs 4,000 km in a month, total cost per km is:
- Materials returned from the contract site to the stores are:
- Input is 2,000 units, normal loss 10% at the start (no scrap), completed units 1,500, closing WIP 200 units 60% converted (materials 100%)…
- In contract costing, work certified means:
- A school bus incurs Rs 72,000 a month, carries an average of 30 students and covers 2,400 km a month. Cost per student-km is:
- A contract is more than 50% complete. Notional profit is Rs 3,00,000 and cash received is 80% of work certified. Profit to be taken…