Business LawsVery hard

A engages B to build a wall, but B refuses to do the work on the date. A treats the contract as continuing and, before the date of performance, a supervening illegality makes performance unlawful. A's right to damages

  1. A. Continues in full
  2. B. Is lost because the contract is discharged by supervening impossibility (Avery v Bowden)
  3. C. Is increased
  4. D. Arises under s.74

Correct answer: B. Is lost because the contract is discharged by supervening impossibility (Avery v Bowden)

If the promisee keeps the contract alive after anticipatory breach, he runs the risk of subsequent frustration that discharges the contract (Avery v Bowden).