The client's product owner Gaurav says the demo was 'not what we asked for', although the sign-off minutes list the data fields as agreed. Tension is high. What is the BEST course of action?

  1. A. Listen, compare the delivered work with the signed minutes side by side, and agree whether to treat the gap as a defect or change request
  2. B. Show the minutes and insist the client approved it, because the team is under pressure already
  3. C. Redo the work at no charge immediately, since that has worked on earlier projects
  4. D. Escalate to Capgemini's director before talking again with Gaurav, to keep things moving for everyone

Correct answer: A. Listen, compare the delivered work with the signed minutes side by side, and agree whether to treat the gap as a defect or change request

Seeing the evidence together depersonalises the dispute and leads to a fair classification; unilateral concession or confrontation escalates cost or conflict.