Behavioural CompetencyHard
Kavya notices that the project's burn-up chart reports green, but Kavya's own analysis suggests the integration is two weeks behind. The status is reviewed by the client monthly. What is the BEST course of action?
- A. Assume the manager knows better and leave it
- B. Share your analysis with the project manager with evidence and suggest updating the status or the underlying measures
- C. Update the status yourself to amber
- D. Mention it to the client at the review to be transparent
Correct answer: B. Share your analysis with the project manager with evidence and suggest updating the status or the underlying measures
The project manager owns the status; presenting evidence lets them correct it. Changing it yourself or telling the client first bypasses ownership.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Rohan learns that a data-centre storage array that the project relies on will be migrated next month, with no communication to the project…
- Nikhil realises midway through a documentation task that the estimate was too low and the work will overrun by two days. The task is not…
- Aarav accidentally emails a spreadsheet containing identity document personal data of 120 customers to the wrong external domain. No one…
- A banking client asks Rahul to add a extra user role that is not in the signed scope, saying it is 'a small thing' and promising a good…
- The client changes the UI design for the third time in two weeks. Siddharth's team is exhausted, the budget is nearly spent, and the…
- Rahul, an offshore analyst, is asked by the onsite coordinator to share daily progress updates three times a day, which Rahul finds…