Civil EngineeringVery hard
By Webster's method, for total lost time L = 16 s per cycle and critical flow ratios 0.25, 0.1, 0.12, the optimum cycle time is
- A. 61.7 s
- B. 39.6 s
- C. 54.7 s
- D. 15.4 s
Correct answer: C. 54.7 s
Y = 0.47; C0 = (1.5L+5)/(1−Y) = 29.0/0.53 = 54.7 s.
Practise more Transportation, Surveying & Estimation (Civil) questionsTransportation, Surveying & Estimation (Civil): notes and key points
More Transportation, Surveying & Estimation (Civil) questions
- By Webster's method, for total lost time L = 10 s per cycle and critical flow ratios 0.15, 0.1, 0.18, the optimum cycle time is
- A two-phase signal has lost time 16 s per cycle and critical flow ratios 0.3 and 0.2. With Webster's cycle time, the effective green time…
- A two-phase signal has lost time 12 s per cycle and critical flow ratios 0.3 and 0.2. With Webster's cycle time, the effective green time…
- An hourly count is 300 cars, 40 buses, 50 trucks and 200 two-wheelers. Taking PCU values car 1, bus 3, truck 3, two-wheeler 0.5, the…
- Spot speeds of four vehicles are 40, 60, 45, 70 km/h. The space-mean speed is
- In a CBR test the load at 2.5 mm penetration is 9.27 kN (standard loads: 13.24 kN at 2.5 mm and 19.96 kN at 5.0 mm). The CBR value based…