CS FundamentalsVery hardProduct company interview · GATE level
Intermediate COCOMO for an organic project uses Effort = 3.2 x KLOC^1.05 x EAF, where EAF is the product of the cost-driver multipliers. A 20 KLOC project has required reliability high (1.15), product complexity high (1.15), analyst capability high (0.86) and use of tools low (1.10); all other drivers are nominal (1.00). What is the estimated effort?
- A. About 74 person-months
- B. About 93 person-months
- C. About 108 person-months
- D. About 64 person-months
Correct answer: B. About 93 person-months
Nominal effort = 3.2 x 20^1.05 = 3.2 x 23.2 = about 74 PM. EAF = 1.15 x 1.15 x 0.86 x 1.10 = 1.251. Effort = 74.2 x 1.251 = about 93 PM. Adding the percentage changes instead of multiplying (+15 + 15 - 14 + 10 = +26%) gives a similar figure here, but the model multiplies. 74 PM ignores the drivers; 108 PM leaves out the favourable analyst-capability multiplier (0.86); 64 PM applies only that 0.86.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Function point counts with weights in brackets: external inputs - 6 simple (3), 4 average (4), 2 complex (6); external outputs - 5 average…
- A system is estimated at 300 function points, and the chosen language averages 53 lines of code per function point. Using basic COCOMO for…
- A program has 12 distinct operators, 20 distinct operands, 90 total operator occurrences and 70 total operand occurrences. Using…
- Activities (duration in days; predecessors): A (4; -), B (6; -), C (3; A), D (5; A), E (4; B, C), F (7; B), G (3; D, E), H (2; F, G), I…
- Activities (duration in days; predecessors): A (3; -), B (5; A), C (4; A), D (2; C), E (6; B), F (5; C), G (4; B, D), H (3; E, F, G). How…
- Activities (normal days, crash limit days, crash cost per day saved; predecessors): A (5, 3, ₹400; -), B (7, 5, ₹300; -), C (4, 3, ₹250…