CS FundamentalsVery hardProduct company interview · GATE level
A system is estimated at 300 function points, and the chosen language averages 53 lines of code per function point. Using basic COCOMO for an organic project (Effort = 2.4 x KLOC^1.05 person-months, Time = 2.5 x Effort^0.38 months), what are the effort, the schedule and the average team size?
- A. About 44 PM, 4.2 months, 10.5 people
- B. About 38 PM, 10.0 months, 3.8 people
- C. About 44 PM, 10.5 months, 462 people
- D. About 44 PM, 10.5 months, 4.2 people
Correct answer: D. About 44 PM, 10.5 months, 4.2 people
Size = 300 x 53 = 15,900 LOC = 15.9 KLOC. Effort = 2.4 x 15.9^1.05 = 2.4 x 18.3 = about 44 PM. Time = 2.5 x 44^0.38 = 2.5 x 4.2 = about 10.5 months. Staff = 44/10.5 = about 4.2 people. Swapping the last two figures (4.2 months, 10.5 people) is the usual slip; 38 PM drops the exponent (2.4 x 15.9). Note that the formula takes KLOC: feeding in 15,900 would give an absurd 60,000+ PM.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A program has 12 distinct operators, 20 distinct operands, 90 total operator occurrences and 70 total operand occurrences. Using…
- Activities (duration in days; predecessors): A (4; -), B (6; -), C (3; A), D (5; A), E (4; B, C), F (7; B), G (3; D, E), H (2; F, G), I…
- Activities (duration in days; predecessors): A (3; -), B (5; A), C (4; A), D (2; C), E (6; B), F (5; C), G (4; B, D), H (3; E, F, G). How…
- Activities (normal days, crash limit days, crash cost per day saved; predecessors): A (5, 3, ₹400; -), B (7, 5, ₹300; -), C (4, 3, ₹250…
- A project's critical path has four activities with three-point estimates (optimistic, most likely, pessimistic) in weeks: (2, 4, 6), (3…
- A project has a budget at completion (BAC) of ₹400 lakh. At the end of month 5 the planned value is ₹180 lakh, the earned value ₹150 lakh…