CS FundamentalsVery hardProduct company interview · GATE level
Function point counts with weights in brackets: external inputs - 6 simple (3), 4 average (4), 2 complex (6); external outputs - 5 average (5), 3 complex (7); external inquiries - 4 simple (3); internal logical files - 3 average (10), 1 complex (15); external interface files - 2 simple (5). The 14 general system characteristics sum to 38, and VAF = 0.65 + 0.01 x (sum). What is the adjusted function point count?
- A. About 170.1
- B. About 159.0
- C. About 163.8
- D. About 103.4
Correct answer: C. About 163.8
Unadjusted FP: inputs 18 + 16 + 12 = 46; outputs 25 + 21 = 46; inquiries 12; internal files 30 + 15 = 45; interface files 10. Total UFP = 159. VAF = 0.65 + 0.38 = 1.03, so FP = 159 x 1.03 = 163.77. 159 skips the adjustment; 170.1 uses a VAF of 1.07 (sum 42); 103.4 uses 0.65 alone, forgetting to add the characteristics.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A system is estimated at 300 function points, and the chosen language averages 53 lines of code per function point. Using basic COCOMO for…
- A program has 12 distinct operators, 20 distinct operands, 90 total operator occurrences and 70 total operand occurrences. Using…
- Activities (duration in days; predecessors): A (4; -), B (6; -), C (3; A), D (5; A), E (4; B, C), F (7; B), G (3; D, E), H (2; F, G), I…
- Activities (duration in days; predecessors): A (3; -), B (5; A), C (4; A), D (2; C), E (6; B), F (5; C), G (4; B, D), H (3; E, F, G). How…
- Activities (normal days, crash limit days, crash cost per day saved; predecessors): A (5, 3, ₹400; -), B (7, 5, ₹300; -), C (4, 3, ₹250…
- A project's critical path has four activities with three-point estimates (optimistic, most likely, pessimistic) in weeks: (2, 4, 6), (3…