CS FundamentalsVery hardProduct company interview · GATE level
A risk has probability 0.4 and would cost ₹50 lakh. Three mitigations are proposed: M1 costs ₹6 lakh and cuts the probability to 0.1; M2 costs ₹4 lakh and cuts the probability to 0.3 and the loss to ₹20 lakh; M3 costs ₹2 lakh and cuts the probability to 0.2. Using risk reduction leverage = (exposure before - exposure after) / cost of mitigation, which is the best option and what is its leverage?
- A. M1, leverage 15
- B. M1, leverage 2.5
- C. M2, leverage 3.5
- D. M3, leverage 5.0
Correct answer: D. M3, leverage 5.0
Exposure before = 0.4 x 50 = ₹20 lakh. M1: after 0.1 x 50 = 5, leverage (20 - 5)/6 = 2.5. M2: after 0.3 x 20 = 6, leverage (20 - 6)/4 = 3.5. M3: after 0.2 x 50 = 10, leverage (20 - 10)/2 = 5.0. M1 removes the most exposure (15) but is the least cost-effective; choosing by absolute reduction instead of reduction per rupee is the trap.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A Kanban team has on average 24 work items in progress and completes 8 items per week. By Little's law, what is the average lead time? If…
- A triple modular redundancy (TMR) design runs three identical modules and a voter that outputs the majority. Each module has reliability…
- A project's unadjusted function point count is 250. After the 14 general system characteristics are rated (0-5 each), the adjusted count…
- A system has 200 unadjusted function points. Using the IFPUG value adjustment factor (14 characteristics, each rated 0 to 5), what is the…
- Basic COCOMO for an embedded-mode project uses Effort = 3.6 x KLOC^1.20 person-months and Time = 2.5 x Effort^0.32 months. For a 50 KLOC…
- In basic COCOMO, embedded-mode effort grows as KLOC^1.20. If the size of an embedded project doubles, what happens to effort and to…