Mid-sprint, the Product Owner asks the Developers to also add a small new item. The Sprint Goal is not at risk. What does Scrum allow?

  1. A. Nothing may change once the sprint starts
  2. B. The Scrum Master decides whether to accept it
  3. C. Scope may be clarified and renegotiated with the Product Owner as more is learned, as long as quality does not drop and the Sprint Goal is not endangered
  4. D. The sprint must be cancelled and replanned

Correct answer: C. Scope may be clarified and renegotiated with the Product Owner as more is learned, as long as quality does not drop and the Sprint Goal is not endangered

The Sprint Backlog belongs to the Developers and can evolve during the sprint; the Sprint Goal and quality stay fixed. A rigid 'no change' rule is a myth, but neither can outsiders impose work.