CS FundamentalsModerateAccenture · Infosys
For a one-month sprint the Scrum Guide sets maximum timeboxes of 8 hours for Sprint Planning, 4 hours for the Sprint Review and 3 hours for the Retrospective. Which statement is correct for a two-week sprint?
- A. The events are usually shorter, and the Daily Scrum stays at 15 minutes
- B. All timeboxes stay the same as for a one-month sprint
- C. The Daily Scrum becomes 30 minutes to compensate
- D. The Retrospective may be skipped every other sprint
Correct answer: A. The events are usually shorter, and the Daily Scrum stays at 15 minutes
The guide gives maximums for a one-month sprint and says shorter sprints usually have shorter events. The Daily Scrum is 15 minutes whatever the sprint length, and no event is optional.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- How many of these are Extreme Programming (XP) practices: (1) pair programming, (2) collective code ownership, (3) continuous integration…
- A backlog contains: 'As a developer, I want to create the database tables for orders.' Which INVEST criterion does it most clearly fail…
- What is the key difference between the incremental and the iterative approaches?
- A team builds a quick prototype only to clarify UI requirements and then discards it, writing the real system from scratch. Another team…
- In Boehm's spiral model, each loop passes through four quadrants. In which quadrant is prototyping mainly used, and for what?
- In the V-model, against which development phase is integration testing designed?