CS FundamentalsHardAccenture · Scrum interview
A sprint burndown chart stays almost flat for the first 8 of 10 days and then drops sharply to zero on the last two days. What is the most likely explanation?
- A. The team is working very efficiently
- B. Stories are too large or being closed only at the end, so progress is not visible until late; the team should slice stories smaller
- C. The Product Owner added scope in the middle
- D. The chart is correct only for Kanban teams
Correct answer: B. Stories are too large or being closed only at the end, so progress is not visible until late; the team should slice stories smaller
Remaining work only falls when items are done. A flat line followed by a cliff signals big batches or late integration and testing, which hides risk; smaller stories give a steadier burn.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A team cannot estimate a story because it depends on an unfamiliar payment API. It schedules a time-boxed 2-day investigation whose output…
- Match each change with its maintenance type. P: fixing a crash reported by users. Q: changing the app to work with a new OS version. R…
- Which pair of Lehman's laws of software evolution best explains why an old in-house ERP becomes steadily harder to change?
- An organisation predicts defect counts and review effectiveness from statistical process-control charts of its historical data, but does…
- In the ISO/IEC 25010 product quality model, which of these is NOT a sub-characteristic of maintainability?
- How many of these statements about Kanban are correct? 1. Kanban prescribes fixed-length iterations. 2. Kanban does not prescribe specific…