CS FundamentalsHardAccenture · Scrum interview

A sprint burndown chart stays almost flat for the first 8 of 10 days and then drops sharply to zero on the last two days. What is the most likely explanation?

  1. A. The team is working very efficiently
  2. B. Stories are too large or being closed only at the end, so progress is not visible until late; the team should slice stories smaller
  3. C. The Product Owner added scope in the middle
  4. D. The chart is correct only for Kanban teams

Correct answer: B. Stories are too large or being closed only at the end, so progress is not visible until late; the team should slice stories smaller

Remaining work only falls when items are done. A flat line followed by a cliff signals big batches or late integration and testing, which hides risk; smaller stories give a steadier burn.