Putnam's software equation implies that, for a fixed size and process productivity, effort varies as 1/t^4, where t is the development time. If management compresses the schedule by 10%, roughly how much does effort change?

  1. A. Rises about 10%
  2. B. Rises about 37%
  3. C. Rises about 52%
  4. D. Falls about 34%

Correct answer: C. Rises about 52%

Effort ratio = 1/0.9^4 ≈ 1.524, a rise of about 52%. Using a cube instead of the fourth power gives about 37%, and 0.9^4 ≈ 0.66 (a 34% fall) applies the relation the wrong way round.