CS FundamentalsVery hardProduct-company placement · GATE CS
Putnam's software equation implies that, for a fixed size and process productivity, effort varies as 1/t^4, where t is the development time. If management compresses the schedule by 10%, roughly how much does effort change?
- A. Rises about 10%
- B. Rises about 37%
- C. Rises about 52%
- D. Falls about 34%
Correct answer: C. Rises about 52%
Effort ratio = 1/0.9^4 ≈ 1.524, a rise of about 52%. Using a cube instead of the fourth power gives about 37%, and 0.9^4 ≈ 0.66 (a 34% fall) applies the relation the wrong way round.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A project has BAC = ₹500 lakh, PV = ₹240 lakh, EV = ₹200 lakh and AC = ₹250 lakh. If both cost and schedule performance are expected to…
- Last sprint, 6 developers working 10 days completed 30 story points. Next sprint 5 developers are available for 9 days each. Using the…
- A single-server queue (M/M/1) serves 10 requests per second. At 8 requests/s the mean response time W = 1/(μ - λ) is 0.5 s. What happens…
- 90% of a CI pipeline's run time is parallelisable tests and 10% is serial setup. Moving to 8 parallel runners, what overall speed-up does…
- A suite of 1,200 tests averaging 3 seconds each is split evenly across 6 parallel shards, and each shard needs 2 minutes of setup before…
- A cache answers 90% of reads in 2 ms; on a miss the read takes 50 ms in total (cache check plus database). What is the average read…