CS FundamentalsHardProduct-company placement · Kanban interview
A customer requests a feature on 1 March; the team starts work on it on 10 March and delivers it on 15 March. Using common Kanban definitions, what are the lead time and the cycle time?
- A. Lead time 5 days, cycle time 14 days
- B. Both 14 days
- C. Lead time 14 days, cycle time 5 days
- D. Lead time 9 days, cycle time 5 days
Correct answer: C. Lead time 14 days, cycle time 5 days
Lead time runs from request to delivery (1 to 15 March = 14 days), as the customer sees it; cycle time runs from start of work to delivery (10 to 15 = 5 days). The 9 days waiting is queue time.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- According to the 2020 Scrum Guide, how many of these are true? 1. An Increment may be delivered to stakeholders before the end of the…
- A fragment contains total = 0 immediately followed by total = compute(), with no use of total in between, and later print(rate) where rate…
- In domain testing for integer inputs, a program accepts points satisfying x + y ≤ 10 (a closed boundary). Which pair of test points is the…
- A task has optimistic 4 days, most likely 6 days and pessimistic 20 days. What are the triangular-distribution mean (a + m + b)/3 and the…
- In IFPUG function-point counting, which of these is an external output (EO) rather than an external inquiry (EQ)?
- A database cluster needs each replica to keep a stable network name (db-0, db-1, db-2) and its own persistent volume across restarts…