A project planned to finish in month 10 actually finishes in month 13. Why does its schedule performance index (SPI = EV / PV) show 1.0 at the end?

  1. A. Because EV is reset to zero once the planned finish date has passed
  2. B. Because PV keeps rising after the plan ends, so SPI drifts back to 1.0
  3. C. Because SPI is computed from cost data, so it simply ignores any delay
  4. D. Because PV equals BAC after the planned end, as does EV at completion

Correct answer: D. Because PV equals BAC after the planned end, as does EV at completion

SPI uses money, not time: after month 10 PV stays at BAC, and when all work is done EV = BAC, so SPI = 1 however late. Earned schedule (SPI(t)) was introduced to fix this.