CS FundamentalsVery hardService-company placement · project management
A project planned to finish in month 10 actually finishes in month 13. Why does its schedule performance index (SPI = EV / PV) show 1.0 at the end?
- A. Because EV is reset to zero once the planned finish date has passed
- B. Because PV keeps rising after the plan ends, so SPI drifts back to 1.0
- C. Because SPI is computed from cost data, so it simply ignores any delay
- D. Because PV equals BAC after the planned end, as does EV at completion
Correct answer: D. Because PV equals BAC after the planned end, as does EV at completion
SPI uses money, not time: after month 10 PV stays at BAC, and when all work is done EV = BAC, so SPI = 1 however late. Earned schedule (SPI(t)) was introduced to fix this.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- An activity not on the critical path has a total float of 3 days and a free float of 1 day. It is delayed by 5 days, and nothing else…
- Which loop invariant lets you prove this binary search correct for a sorted list a? python lo, hi = 0, len(a) - 1 while lo <= hi: mid =…
- A team has 40 open defects; 15 new ones arrive and 25 are fixed each week. If these rates hold, how long until the backlog is cleared?
- Which statement correctly contrasts a centralised VCS such as Subversion with Git?
- Two artists keep overwriting each other's edits to the same layered .psd file in Git. Why does the usual merge workflow fail, and what…
- Priya rebases Rahul's three commits onto the latest main. What happens to the author and committer fields of the rewritten commits?