CS FundamentalsHardGATE CS · Software Engineering · Advanced
Basic COCOMO for an embedded-mode project uses effort E = 3.6 (KLOC)^1.20 person-months and development time D = 2.5 E^0.32 months. For a 45 KLOC project, what is the average staffing level E / D, to one decimal place?
- A. 8.2 persons
- B. 15.0 persons
- C. 13.1 persons
- D. 21.3 persons
Correct answer: D. 21.3 persons
E = 3.6 x 45^1.2 = 347 person-months, D = 2.5 x E^0.32 = 16.2 months, so staffing = 21.3 persons. The semi-detached or organic constants give 13.1 and 8.2.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A program has 14 distinct operators, 22 distinct operands, 82 operator occurrences and 61 operand occurrences. Using Halstead's measures…
- The control-flow graphs of a program's two separate routines have E = 16, N = 13 and E = 9, N = 8 edges and nodes respectively (each graph…
- A project has these activities (duration in days; predecessors): A (3; none), B (4; none), C (5; A), D (2; A, B), E (6; B), F (4; C, D), G…
- The critical path of a project has four activities with (optimistic, most likely, pessimistic) durations in days: (2, 4, 8), (3, 5, 13)…
- A system has component A (reliability 0.98) in series with a parallel pair B (0.90) and C (0.85) - the pair works if at least one works…
- A server has MTTF = 400 hours and MTTR = 8 hours. Two identical servers run in active-active mode (the service is up if at least one…