Basic COCOMO for an embedded-mode project uses effort E = 3.6 (KLOC)^1.20 person-months and development time D = 2.5 E^0.32 months. For a 45 KLOC project, what is the average staffing level E / D, to one decimal place?

  1. A. 8.2 persons
  2. B. 15.0 persons
  3. C. 13.1 persons
  4. D. 21.3 persons

Correct answer: D. 21.3 persons

E = 3.6 x 45^1.2 = 347 person-months, D = 2.5 x E^0.32 = 16.2 months, so staffing = 21.3 persons. The semi-detached or organic constants give 13.1 and 8.2.