CS FundamentalsVery hardGATE CS · Software Engineering · Advanced
The critical path of a project has four activities with (optimistic, most likely, pessimistic) durations in days: (2, 4, 8), (3, 5, 13), (1, 2, 3) and (4, 6, 14), treated as independent with PERT beta estimates (mean (o + 4m + p)/6, variance ((p - o)/6)^2). Using the normal approximation for the path length, what is the probability of finishing within 22 days?
- A. 0.15
- B. 0.85
- C. 0.97
- D. 0.66
Correct answer: B. 0.85
Mean = 19.33 days, variance = 6.667, so sigma = 2.58. z = (22 - 19.33)/2.58 = 1.03, giving a probability of about 0.85. Using the variance instead of sigma, or the most-likely sum as the mean, gives other values.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A system has component A (reliability 0.98) in series with a parallel pair B (0.90) and C (0.85) - the pair works if at least one works…
- A server has MTTF = 400 hours and MTTR = 8 hours. Two identical servers run in active-active mode (the service is up if at least one…
- Which list orders these module-cohesion types from the most desirable (strongest) to the least desirable (weakest)?
- In the Jelinski-Moranda reliability model a program starts with N = 10 faults, each fault contributes a failure rate of 0.02 per hour, and…
- Four independent defect-removal activities remove 60%, 50%, 55% and 70% of the defects present when they run (each acts on what the…
- A project has a budget at completion of 800 units. After some time 60% of the work was planned to be complete, 45% is actually complete…