CS FundamentalsVery hardGATE CS · Software Engineering · Advanced

The critical path of a project has four activities with (optimistic, most likely, pessimistic) durations in days: (2, 4, 8), (3, 5, 13), (1, 2, 3) and (4, 6, 14), treated as independent with PERT beta estimates (mean (o + 4m + p)/6, variance ((p - o)/6)^2). Using the normal approximation for the path length, what is the probability of finishing within 22 days?

  1. A. 0.15
  2. B. 0.85
  3. C. 0.97
  4. D. 0.66

Correct answer: B. 0.85

Mean = 19.33 days, variance = 6.667, so sigma = 2.58. z = (22 - 19.33)/2.58 = 1.03, giving a probability of about 0.85. Using the variance instead of sigma, or the most-likely sum as the mean, gives other values.