CS FundamentalsVery hardGATE CS · Software Engineering · Advanced
In the Jelinski-Moranda reliability model a program starts with N = 10 faults, each fault contributes a failure rate of 0.02 per hour, and each failure is followed by perfect removal of exactly one fault. What is the expected total operating time until the 6th failure occurs?
- A. 42.3 hours
- B. 30.0 hours
- C. 37.3 hours
- D. 52.3 hours
Correct answer: A. 42.3 hours
Before the i-th failure the rate is 0.02 x (10 - i + 1), so the expected gap is 1/rate. Summing gaps for i = 1..6: 5 + 5.56 + 6.25 + 7.14 + 8.33 + 10 = 42.3 hours. A constant rate would give 30.0 hours.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Four independent defect-removal activities remove 60%, 50%, 55% and 70% of the defects present when they run (each acts on what the…
- A project has a budget at completion of 800 units. After some time 60% of the work was planned to be complete, 45% is actually complete…
- The decision (A and B) or (C and D) contains four conditions. What is the minimum number of test cases that achieves 100% modified…
- A routine takes three integer inputs a, b, c, each with a valid range [min, max] with min < max - 1, and one boolean flag f. Under…
- A configuration has 4 parameters with 3 possible values each. What is the minimum number of test cases needed to cover every pair of…
- A team of 6 developers is increased to 9 developers to catch up on a late project. If every pair of team members needs one communication…