A project has these activities (duration in days; predecessors): A (3; none), B (4; none), C (5; A), D (2; A, B), E (6; B), F (4; C, D), G (3; D, E), H (5; F, G). What are the project duration and the total float of activity D?
- A. 19 days, float 3 days
- B. 18 days, float 3 days
- C. 17 days, float 3 days
- D. 18 days, float 4 days
Correct answer: B. 18 days, float 3 days
Forward pass gives the earliest finish times, the backward pass the latest start times. Project duration 18 days; for D, latest start 7 minus earliest start 4 = float 3. Critical activities (zero float): B, E, G, H.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- The critical path of a project has four activities with (optimistic, most likely, pessimistic) durations in days: (2, 4, 8), (3, 5, 13)…
- A system has component A (reliability 0.98) in series with a parallel pair B (0.90) and C (0.85) - the pair works if at least one works…
- A server has MTTF = 400 hours and MTTR = 8 hours. Two identical servers run in active-active mode (the service is up if at least one…
- Which list orders these module-cohesion types from the most desirable (strongest) to the least desirable (weakest)?
- In the Jelinski-Moranda reliability model a program starts with N = 10 faults, each fault contributes a failure rate of 0.02 per hour, and…
- Four independent defect-removal activities remove 60%, 50%, 55% and 70% of the defects present when they run (each acts on what the…