A project has these activities (duration in days; predecessors): A (3; none), B (4; none), C (5; A), D (2; A, B), E (6; B), F (4; C, D), G (3; D, E), H (5; F, G). What are the project duration and the total float of activity D?

  1. A. 19 days, float 3 days
  2. B. 18 days, float 3 days
  3. C. 17 days, float 3 days
  4. D. 18 days, float 4 days

Correct answer: B. 18 days, float 3 days

Forward pass gives the earliest finish times, the backward pass the latest start times. Project duration 18 days; for D, latest start 7 minus earliest start 4 = float 3. Critical activities (zero float): B, E, G, H.