A Scrum team completed 24, 30 and 27 story points in its last three sprints. The remaining backlog is 162 points. Using average velocity, how many sprints are needed?
- A. 6
- B. 5
- C. 7
- D. 9
Correct answer: A. 6
Average velocity = (24 + 30 + 27)/3 = 27 points per sprint; 162/27 = 6 sprints.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A developer checks out a specific commit by its hash and makes two new commits, then switches to main without creating a branch. What is…
- In Basic COCOMO (organic mode, Effort = 2.4 x (KLOC)^1.05 person-months), what is the approximate effort for a 10 KLOC project?
- A task has optimistic 4 days, most likely 6 days and pessimistic 14 days. What is the PERT expected duration?
- Which deployment strategy releases a new version to a small subset of users first and widens the rollout gradually while monitoring?
- Why is it advised not to run git rebase on commits already pushed to a shared branch?
- A module of 30,000 lines of code has 45 defects found in testing. What is the defect density?