Match each project situation with the most suitable SDLC model. P. Requirements fixed and well understood, short project Q. Large, high-risk project where risks must be evaluated each cycle R. Customer cannot state requirements until they see a working mock-up S. Requirements evolve; working software is needed every 2 weeks 1. Agile (Scrum) 2. Prototype 3. Spiral 4. Waterfall

  1. A. P-4, Q-2, R-3, S-1
  2. B. P-1, Q-3, R-2, S-4
  3. C. P-4, Q-3, R-2, S-1
  4. D. P-3, Q-4, R-2, S-1

Correct answer: C. P-4, Q-3, R-2, S-1

Stable requirements → Waterfall (4); risk-driven → Spiral (3); unclear requirements clarified by a mock-up → Prototype (2); evolving requirements with frequent delivery → Agile (1).