A project faces three risks: A: probability 0.3, loss ₹5 lakh B: probability 0.6, loss ₹2 lakh C: probability 0.1, loss ₹12 lakh Ranking by risk exposure, which should be addressed first?
- A. B
- B. C
- C. B and C equally, ahead of A
- D. A
Correct answer: D. A
Risk exposure = probability × loss: A = 1.5 lakh, B = 1.2 lakh, C = 1.2 lakh. A is highest. Picking C looks only at the size of the loss; picking B looks only at the probability.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A team commits 40 story points to a 10-day sprint. After day 6, the burndown chart shows 28 points remaining. If work continues at the…
- A library following Semantic Versioning is at version 2.4.7. The next release removes a public method that clients may be calling. What…
- A bug exists at the current commit but not at a commit 200 commits earlier. Using git bisect (a binary search through history), what is…
- What distinguishes continuous deployment from continuous delivery?
- In a unit test, the real payment gateway is replaced by an object that records calls so that the test can assert “charge() was called…
- Using a three-point PERT estimate, a task has optimistic time 4 days, most likely 6 days and pessimistic 14 days. What is the expected…