Mechanical EngineeringVery hard
Using exponential smoothing with α = 0.3, the forecast for period 1 was 100. Actual demands were 90 (period 1) and 100 (period 2). The forecast for period 3 is
- A. 122.37
- B. 78.32
- C. 93.00
- D. 97.90
Correct answer: D. 97.90
F2 = 0.3×90 + 0.7×100 = 97.00; F3 = 0.3×100 + 0.7×97.00 = 97.90.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- Using exponential smoothing with α = 0.3, the forecast for period 1 was 150. Actual demands were 130 (period 1) and 140 (period 2). The…
- A product sells at ₹50 per unit with a variable cost of ₹40 per unit and fixed costs of ₹60000. The number of units to earn a profit of…
- A product sells at ₹80 per unit with a variable cost of ₹40 per unit and fixed costs of ₹90000. The number of units to earn a profit of…
- A product sells at ₹50 per unit with a variable cost of ₹20 per unit and fixed costs of ₹60000. The number of units to earn a profit of…
- Maximise Z = 5x + 3y subject to 2x + 2y ≤ 12, 2x + 1y ≤ 18, x, y ≥ 0. The optimum value of Z is
- Maximise Z = 4x + 5y subject to 2x + 3y ≤ 18, 2x + 1y ≤ 12, x, y ≥ 0. The optimum value of Z is