Mechanical EngineeringVery hard

Using exponential smoothing with α = 0.3, the forecast for period 1 was 150. Actual demands were 130 (period 1) and 140 (period 2). The forecast for period 3 is

  1. A. 135.00
  2. B. 142.80
  3. C. 178.50
  4. D. 133.00

Correct answer: B. 142.80

F2 = 0.3×130 + 0.7×150 = 144.00; F3 = 0.3×140 + 0.7×144.00 = 142.80.