Mechanical EngineeringVery hard
Maximise Z = 5x + 3y subject to 2x + 2y ≤ 12, 2x + 1y ≤ 18, x, y ≥ 0. The optimum value of Z is
- A. 54.00
- B. 45.00
- C. 42.00
- D. 30.00
Correct answer: D. 30.00
Evaluate Z at the feasible corner points of the region; the maximum is 30.00.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- Maximise Z = 4x + 5y subject to 2x + 3y ≤ 18, 2x + 1y ≤ 12, x, y ≥ 0. The optimum value of Z is
- A PERT activity has optimistic time 2 days, most likely time 4 days and pessimistic time 6 days. The expected duration is
- The critical path of a project has three activities with (a, m, b) times of (2, 3, 8), (4, 5, 10), (3, 6, 9) days. The Z-value for…
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (4 days), both followed by D (2 days). The minimum…
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (9 days), both followed by D (3 days). The minimum…
- A product needs a total work content of 60 min. The line must make 40 units in an available time of 450 min. Taking the theoretical…